In multi-silo plants, correct connection and target-silo readiness are required before filling. This scenario jointly assesses connection control and silo-monitoring needs.
Questions the operator must answer
How many silos and filling connections exist? Which material may enter which silo? Where does the operator see filling authorization? Which equipment stops filling on level or pressure alarms?
Commissioning scope
Prepare a test plan for authorization, warning, shutdown and restart behavior. Define thresholds, timing and fault behavior according to the plant risk assessment and manufacturer instructions.
| Industry | Cement and building materials |
| Material | Pneumatically conveyed powdered raw material |
| Process | Tanker → filling connection → silo |
Problem and measurement challenge
Wrong-line connection, attempted filling of a full silo and pressure changes during filling.
Technology selection
Connection detection and hose/line identification are separate tasks. Define coded coupling, connection detection, level and pressure monitoring needs individually.
Installation and technical notes
Review existing coupling, filling pipe, silo drawing, control panel and signaling points during site assessment.